Brief information up to 01.08.2017
Total cost of the project: |
- 115 300 000 USD |
Asian Development Bank (Grant) OPEC Fund (Credit) |
- 100 000 000 USD - 14 000 000 USD |
Contribution of the Government of the Republic of Tajikistan |
- 1 300 000 USD |
|
|
Disbursement from the beginning of the project:
|
-114 614000 USD (99,4%) |
Beginning of the project: November 2012
Completion of the project: December 2016
Consultant: “Kocks” (Germany)
Contractor: “Sindzyan Beysin” (China)
Project description:
- rehabilitation of 112.6 km of road,
- construction and reconstruction of 31 bridges,
- improvement of the infrastructure of the customs post “Sarazm”,
- purchase of the equipment for road maintenance (32 items),
- repair of 60 km of local roads.
- October 18, 2015 – with participation of the President of the country his Excellency Emomalii Rahmon was held an opening ceremony of the object.
Component “Improvement of the infrastructure of the customs post “Sarazm”.
October 20, 2015 – signing of the contract between Ministry of Transport of the Republic of Tajikistan and “Sokhtmon”, Ltd for implementation of the component “Improvement of the infrastructure of the customs post “Sarazm”.
Component “Repairof 60 kmoflocalroads”
June 9, 2015 – based on the contract signed with “Sindzyan Beysin” (China) all works for repair of local roads were completed on July, 2016.
August 11, 2016 – the object was accepted by working commission and now it is on warranty period..
Component “Purchase of the equipment for road maintenance”
June 10, 2015 – signing of the contract with “ХGМА” (China) for purchase of the equipment for road maintenance. 32 items of equipment for road maintenance were delivered.