• Tajik
  • Русский
  • English

 

 

- Total cost – USD 1,0 million, including;

           • Islamic Republic of Iran Government’s grant – USD 1,0 million

- contractor: Metra consulting engineering company (Iran)

- beginning of the project - August 2011, end of the project - August 2012

            - description of the project: selection of railway route, gathering of all necessary datas and after the economic, financial and technical analyzes to determine the probability of construction of standard railway (1435 mm) inside Tajikistan based on them

- utilization of funds - 20%

- in the second quarter of 2013 the project works have been ceased by the contractor due to nonpayment of consultancy services from Iranian side for the amount up to USD 285,0 thousand

 

Chart of implementation of construction works

 

 

Title of works

The percentage of completion (%)

1

Preparation of the report "Data collection and analysis"

100

2

Preparation of the report "Plan preliminary operation (Transport offer)"

100

3

Preparation of the report "Analysis and Forecast of railway market "

100

4

Preparation of the report "Project proposal (Project design)"

100