                        Brief information up to 01.08.2017

Total cost of the project:

- 54 000 000 USD

World Bank (Credit)

World Bank (Grant)

Contribution of the Government of the Republic of Tajikistan

Disbursement from the beginning of the project:

- 38 250 000 USD

-   6 750 000 USD

-   9 000 000 USD

 - 12 639 000 USD (23.4%)

- April 16, 2015 – signing of the Credit and Grant agreements between Government of the Republic of Tajikistan and World Bank,

- March 28, 2016 – signing of the contract between Ministry of Transport and “Dohwa Engineering” (Korea) for consulting services for constructon supervision,

- March 28, 2016 – signing of the contract between Ministry of Transport and China Railway Wuju (Group) Corporation (China) for cvil works,

- were hired 10 individual consultants for Project Implementation Group including,

- January 27, 2016 – was held a tender for purchase of the vihicles for PIG. The contract with “Business Project Management”, Ltd was signed on April 7, 2016,

- February 17, 2016 – was held a tender on purchase of traffic counters and roughness profiler. Contracts were signed with “Shaid”, Ltd on April 7, 2016 Equipment is already delivered to the Ministry of Transport

Number of staff:                       total – 413persons

                                                local – 364 persons (88%)

                                                foreigners – 49 persons (12%)     

Number of equipment – 112 items.