• Tajik
  • Русский
  • English

                                                Brief information up to 01.08.2017 

Total cost of the project:

- 131 200 000 USD

Asian Development Bank (Grant)

- 120 000 000 USD

Contribution of the Government of the Republic of Tajikistan

- 11 200 000 USD

Disbursement from the beginning of the project

- 125 100 000 USD  

  (95%)

Beginning of the project:    October 2011

Completion of the project:  March 2016

Consultant: SMEC International (Australia)

Contractor: China Road and Bridge Construction Corporation (China)

Project description:

- rehabilitation of 57 km of road,

- construction and reconstruction of 9 bridges,

- improvement of the infrastructure of the customs post “Dusti”,

- gender program (allocation of funds for the development of small business for women from low-income families.

September 12, 2015 – a preliminary acceptance of the object by the Working commission. The object is on guarantee period now (24 month). Currently the the remarks that were revealed by the Working commission are being removed.

September 18, 2015 - 18.09.2015г. – with participation of leadership of the country was held an official  commissioning of the road.

May 27, 2017 – a decree on creation of a state acceptance commission was approved by the Government of the Republic of Tajikistan and the object is being prepared for the commissioning.